21/08/2019

Self-Build Part 3: Contractor Issues

Welcome to the last in our three-part series on how to avoid common pitfalls in Self Build projects. This final blog post discusses some of the common issues which arise when working with Contractors, and how to avoid them.

Read more

Close

Welcome to the last in our three-part series on how to avoid common pitfalls in Self Build projects. This final blog post discusses some of the common issues which arise when working with Contractors, and how to avoid them.

 

So, what are the most common issues?

 

  1. Insufficient detail at tender stage resulting in additional cost and time risk to the client.
  2. Choosing a ‘bad’ contractor
  3. Inadequate or absent Construction Contract, and no Contract Administrator resulting in risk to the client
  4. Project delays caused by contractor, and inadequate recourse.

 

The result?

Projects going over budget

 

The solution?

Chose the right contractor, and the right construction contract

 

Tendering the right information

 

Your design is finalised, Planning Approval granted, and you are working through the detailed design with your design team. At this point you will need to consider what information you will be producing for the contractors to price, and once again there is a choice of the level of risk you are willing to accept.

 

There are two main options for producing information for pricing, and each has their own pros and cons.

 

The first, and simplest, is to get the contractor to price on the basis of the Specification and Drawings. In this instance, the contractor is required to undertake a full measure of the drawings and specification provided, to enable them to cost the project. The advantage of this method is that you do not have to employ a quantity surveyor for this option; your architect will, if appointed to do so, be able to tender this on your behalf. However, there is a risk associated with it.

 

It’s worth remembering that measuring the quantities required for a building is a lot of work. Most small contractors either have a single in-house estimator to do their tendering, valuing and billing, or perhaps they employ a third party to do this for them. This therefore has a cost associated for the contractor. And, assuming you are tendering to three or more contractors, each contractor will know they only have a 1/3 chance of securing the project. They will therefore not want to lose money on pricing a project with a low chance of success. It is therefore firstly pretty certain that they will build the costs of tendering into their tender figure somehow, probably through increased overheads and profit, to ensure that they makes their money back if they wins the work.

 

Secondly, in case they are not successful, they will want to keep their costs to a minimum. The contractor may therefore not measure as accurately as they otherwise might, and may just add inflated figures for the sake of speed, artificially inflating the overall tender sum. There’s relatively little risk in this for them, as the know that the other contractors will be likely to be doing the same!

 

It’s worth also noting that with this option, you are unlikely to get much of a breakdown of the tender figure you receive, therefore won’t be able to spot these inflated figures. It will make comparison between tendering contractors more difficult, and errors or discrepancies more tricky to spot. A further risk to you as the client is that any errors or omissions within the drawings or specification will not have been priced, and will therefore cost you extra. If it isn’t expressly stated somewhere in the documents, it won’t have been priced.

 

The second option available to you is to employ your Quantity Surveyor to produce what is known as a Bill of Quantities. This document is a full and unambiguous measured breakdown of all the building elements, down to the metre length or m2, and is often built upon the cost plan already undertaken with considerably more detail added.

 

This will probably, depending on the size of your house, cost you in the region of £5000 to produce. However, in our experience, contractors who are provided with a bill of quantities find it much easier to price a project, and therefore price more accurately and therefore more competitively. The contractor will be required to provide you with the priced Bill with his tender return, which allows you to both compare one tender to another, and easily spot any areas where you might wish to spend more or need to spend less. It also acts as a very useful tool during the construction stage, as it allows you to easily compare the contractor’s requests for stage payment as the work progresses against the costs in the Bill, thereby ensuring that there are no overly inflated applications for payment being made.

 

So, while there is an upfront cost to you, in our experience that cost is usually more than recouped in lower tender sums and better management. Later on we will talk about construction Contracts, and how these can also be a tool in ensuring that costs and time do not run away with you.

 

Choosing the right contractor

 

It is likely that your architect and quantity surveyor will be able to provide you with a few recommendations for contractors they have worked with before with some success. However, I would always advise not to just take their word for it! We would usually recommend tendering to around three contractors, to give a good range of competition without being excessive. You will therefore probably want a shortlist of five or six to look into. In the first instance, either you or, if appointed for this stage, your architect, should approach the six contractors and ask them if they are interested in tendering for the project. Some may not be; they may be too busy, it may not be in the right area for them, and it’s better to find out now than just sending them the tender ‘cold’.

 

If they are interested, ask them to provide recent client references for projects similar to yours. These need to be names and email addresses or telephone numbers, rather than copies of statements. Ideally, you want to be able to speak to the clients and even, if they’re willing, go and see the houses that the contractor has built to see the quality for yourself.

 

Using a formal contract

 

Choosing the right form of contract for your project is quite a big topic, and has many factors. This is something you should discuss in detail with your architect and they will advise you on the basis of your projects and needs. However, I will make a few pertinent points. Firstly, don’t ever be tempted to not have a formal building contract. By that I mean, do not think that by simply signing a contractor’s terms and conditions and sending an email accepting their quote that you are sufficiently covered if a problem arises. ‘Proper’ Construction Contracts, particularly those produced by the Joint Contracts Tribunal (JCT) and the RIBA, are documents designed to cover all eventualities, and protect both parties from financial risk. They can be lengthy, depending on the form chosen, but are the only way of ensuring that your huge investment is adequately protected. I am focussing here on the JCT contracts, but there are others, and you should follow the advice of your architect.

 

The JCT produce two forms of contract which are suitable for traditionally procured residential new build housing projects, which have their pros and cons. These are the Minor Works contract and the Intermediate Contract. Some clients would opt to utilise the smaller and simpler Minor Works contract, but we always advise that for a new build house, the Intermediate form offers the most appropriate level of security for a client.

 

It is worth noting that for most of the standard building contracts, you as the client are required to appoint a Contract Administrator to manage the contract on your behalf. This must be a person who is able to act impartially (i.e. it cannot be yourself and it cannot be the contractor) and is therefore often the architect. Now while you may pay your architect for undertaking this role, you will find that he has a legal responsibility to act impartially, so be warned that in the case of a dispute he may not always find in your favour.

 

The second point here is a big one. You should never, ever make an upfront payment to the contractor unless you have that payment protected by an advance payment bond; allowances for which are set out within the contract. A builder going bust and you losing your money is the last thing you need.

 

While on the possibility of builders going bust, I’d like to touch on an element of a project known as a Contractor’s Design Portion. As the name suggests, this is an element of a build project for which the contractor is responsible for the design, not just the installation and materials. This is as old as build projects themselves, but the industry has been slow to pick up on the legal and contractual ramifications of them. So, as an example, you would like underfloor heating for your home. On a small project like a house you don’t want to pay an M&E engineer to design the system for you, therefore you leave the design to the contractor’s M&E subcontractor. This would be a contractor design portion. In the old days, that would be that, and there would be nothing specifically in writing within the contract.

 

However, imagine that the underfloor heating goes wrong 6 months after you move in. The system has been designed incorrectly and the whole of the floor of your house has to be broken out and the system reinstalled. The cost of this is high; you have a beautiful polished concrete floor which has to be replaced; the implications of introducing wet concrete and polishing into your finished and furnished house are widespread. The subcontractor goes bust, as he can’t afford the cost to his small business. The responsibility passes up the line to the main contractor. He is also a small contractor. He also goes bust. You are then left with no recourse against anyone, and no heating.

 

So the answer to this is to specify a form of contract which allows for named Contractor’s Design Portions. Both the JCT Minor Works and Intermediate forms have an option to include CDPs to varying degrees. Long story short, the implication of this is that your contractor is required to carry professional indemnity insurance, just like every other design professional. If the subcontractor goes bust, the main contractor’s PI insurance would therefore pick up the tab for the remedial work. This is something which would need to be considered at tender stage. When selecting your contractors you would need to make them aware that there are CDPs, and ensure that they carry PI insurance. Not all contractors do, particularly the smaller ones for whom the risk of having to fold their business is more acceptable than monthly insurance payments. So, one to look out for.

 

The final point to mention in this section is the use of Liquidated and Ascertained Damages within a construction contract. LADs as they’re more commonly known are a weekly or monthly amount of money which is set out within the contract that the contractor must pay to you the client for delays to the completion date of a project, where the delay is the fault of the contractor. Where the delay is down to late decisions or changes, extensions of time to the contract would be granted, but where the delay is down to the contractor, LADs can be deducted from the contractor’s payments. Now it’s important to note that this amount is not a ‘penalty’; you can’t penalise the contractor for being late. However, genuine costs that you might incur such as additional rent if you’re in rented accommodation, or interest payments on financing, or storage costs for your belongings are genuine costs, and can be used to calculate the LADs figure.


So that concludes our three-part whistle-stop tour of the common pitfalls of self-build projects. I hope this is helpful, and please do get in touch if you have any questions.


 

View more blog posts.

Self-Build Part 3: Contractor Issues
Self-Build Part 3: Contractor Issues

Self-Build Part 3: Contractor Issues

Welcome to the last in our three-part series on how to avoid common pitfalls in Self Build projects. This final blog post discusses some of the common issues which arise when working with Contractors, and how to avoid them.

Read more

Close

Self-Build Part 3: Contractor Issues

Welcome to the last in our three-part series on how to avoid common pitfalls in Self Build projects. This final blog post discusses some of the common issues which arise when working with Contractors, and how to avoid them.

 

So, what are the most common issues?

 

  1. Insufficient detail at tender stage resulting in additional cost and time risk to the client.
  2. Choosing a ‘bad’ contractor
  3. Inadequate or absent Construction Contract, and no Contract Administrator resulting in risk to the client
  4. Project delays caused by contractor, and inadequate recourse.

 

The result?

Projects going over budget

 

The solution?

Chose the right contractor, and the right construction contract

 

Tendering the right information

 

Your design is finalised, Planning Approval granted, and you are working through the detailed design with your design team. At this point you will need to consider what information you will be producing for the contractors to price, and once again there is a choice of the level of risk you are willing to accept.

 

There are two main options for producing information for pricing, and each has their own pros and cons.

 

The first, and simplest, is to get the contractor to price on the basis of the Specification and Drawings. In this instance, the contractor is required to undertake a full measure of the drawings and specification provided, to enable them to cost the project. The advantage of this method is that you do not have to employ a quantity surveyor for this option; your architect will, if appointed to do so, be able to tender this on your behalf. However, there is a risk associated with it.

 

It’s worth remembering that measuring the quantities required for a building is a lot of work. Most small contractors either have a single in-house estimator to do their tendering, valuing and billing, or perhaps they employ a third party to do this for them. This therefore has a cost associated for the contractor. And, assuming you are tendering to three or more contractors, each contractor will know they only have a 1/3 chance of securing the project. They will therefore not want to lose money on pricing a project with a low chance of success. It is therefore firstly pretty certain that they will build the costs of tendering into their tender figure somehow, probably through increased overheads and profit, to ensure that they makes their money back if they wins the work.

 

Secondly, in case they are not successful, they will want to keep their costs to a minimum. The contractor may therefore not measure as accurately as they otherwise might, and may just add inflated figures for the sake of speed, artificially inflating the overall tender sum. There’s relatively little risk in this for them, as the know that the other contractors will be likely to be doing the same!

 

It’s worth also noting that with this option, you are unlikely to get much of a breakdown of the tender figure you receive, therefore won’t be able to spot these inflated figures. It will make comparison between tendering contractors more difficult, and errors or discrepancies more tricky to spot. A further risk to you as the client is that any errors or omissions within the drawings or specification will not have been priced, and will therefore cost you extra. If it isn’t expressly stated somewhere in the documents, it won’t have been priced.

 

The second option available to you is to employ your Quantity Surveyor to produce what is known as a Bill of Quantities. This document is a full and unambiguous measured breakdown of all the building elements, down to the metre length or m2, and is often built upon the cost plan already undertaken with considerably more detail added.

 

This will probably, depending on the size of your house, cost you in the region of £5000 to produce. However, in our experience, contractors who are provided with a bill of quantities find it much easier to price a project, and therefore price more accurately and therefore more competitively. The contractor will be required to provide you with the priced Bill with his tender return, which allows you to both compare one tender to another, and easily spot any areas where you might wish to spend more or need to spend less. It also acts as a very useful tool during the construction stage, as it allows you to easily compare the contractor’s requests for stage payment as the work progresses against the costs in the Bill, thereby ensuring that there are no overly inflated applications for payment being made.

 

So, while there is an upfront cost to you, in our experience that cost is usually more than recouped in lower tender sums and better management. Later on we will talk about construction Contracts, and how these can also be a tool in ensuring that costs and time do not run away with you.

 

Choosing the right contractor

 

It is likely that your architect and quantity surveyor will be able to provide you with a few recommendations for contractors they have worked with before with some success. However, I would always advise not to just take their word for it! We would usually recommend tendering to around three contractors, to give a good range of competition without being excessive. You will therefore probably want a shortlist of five or six to look into. In the first instance, either you or, if appointed for this stage, your architect, should approach the six contractors and ask them if they are interested in tendering for the project. Some may not be; they may be too busy, it may not be in the right area for them, and it’s better to find out now than just sending them the tender ‘cold’.

 

If they are interested, ask them to provide recent client references for projects similar to yours. These need to be names and email addresses or telephone numbers, rather than copies of statements. Ideally, you want to be able to speak to the clients and even, if they’re willing, go and see the houses that the contractor has built to see the quality for yourself.

 

Using a formal contract

 

Choosing the right form of contract for your project is quite a big topic, and has many factors. This is something you should discuss in detail with your architect and they will advise you on the basis of your projects and needs. However, I will make a few pertinent points. Firstly, don’t ever be tempted to not have a formal building contract. By that I mean, do not think that by simply signing a contractor’s terms and conditions and sending an email accepting their quote that you are sufficiently covered if a problem arises. ‘Proper’ Construction Contracts, particularly those produced by the Joint Contracts Tribunal (JCT) and the RIBA, are documents designed to cover all eventualities, and protect both parties from financial risk. They can be lengthy, depending on the form chosen, but are the only way of ensuring that your huge investment is adequately protected. I am focussing here on the JCT contracts, but there are others, and you should follow the advice of your architect.

 

The JCT produce two forms of contract which are suitable for traditionally procured residential new build housing projects, which have their pros and cons. These are the Minor Works contract and the Intermediate Contract. Some clients would opt to utilise the smaller and simpler Minor Works contract, but we always advise that for a new build house, the Intermediate form offers the most appropriate level of security for a client.

 

It is worth noting that for most of the standard building contracts, you as the client are required to appoint a Contract Administrator to manage the contract on your behalf. This must be a person who is able to act impartially (i.e. it cannot be yourself and it cannot be the contractor) and is therefore often the architect. Now while you may pay your architect for undertaking this role, you will find that he has a legal responsibility to act impartially, so be warned that in the case of a dispute he may not always find in your favour.

 

The second point here is a big one. You should never, ever make an upfront payment to the contractor unless you have that payment protected by an advance payment bond; allowances for which are set out within the contract. A builder going bust and you losing your money is the last thing you need.

 

While on the possibility of builders going bust, I’d like to touch on an element of a project known as a Contractor’s Design Portion. As the name suggests, this is an element of a build project for which the contractor is responsible for the design, not just the installation and materials. This is as old as build projects themselves, but the industry has been slow to pick up on the legal and contractual ramifications of them. So, as an example, you would like underfloor heating for your home. On a small project like a house you don’t want to pay an M&E engineer to design the system for you, therefore you leave the design to the contractor’s M&E subcontractor. This would be a contractor design portion. In the old days, that would be that, and there would be nothing specifically in writing within the contract.

 

However, imagine that the underfloor heating goes wrong 6 months after you move in. The system has been designed incorrectly and the whole of the floor of your house has to be broken out and the system reinstalled. The cost of this is high; you have a beautiful polished concrete floor which has to be replaced; the implications of introducing wet concrete and polishing into your finished and furnished house are widespread. The subcontractor goes bust, as he can’t afford the cost to his small business. The responsibility passes up the line to the main contractor. He is also a small contractor. He also goes bust. You are then left with no recourse against anyone, and no heating.

 

So the answer to this is to specify a form of contract which allows for named Contractor’s Design Portions. Both the JCT Minor Works and Intermediate forms have an option to include CDPs to varying degrees. Long story short, the implication of this is that your contractor is required to carry professional indemnity insurance, just like every other design professional. If the subcontractor goes bust, the main contractor’s PI insurance would therefore pick up the tab for the remedial work. This is something which would need to be considered at tender stage. When selecting your contractors you would need to make them aware that there are CDPs, and ensure that they carry PI insurance. Not all contractors do, particularly the smaller ones for whom the risk of having to fold their business is more acceptable than monthly insurance payments. So, one to look out for.

 

The final point to mention in this section is the use of Liquidated and Ascertained Damages within a construction contract. LADs as they’re more commonly known are a weekly or monthly amount of money which is set out within the contract that the contractor must pay to you the client for delays to the completion date of a project, where the delay is the fault of the contractor. Where the delay is down to late decisions or changes, extensions of time to the contract would be granted, but where the delay is down to the contractor, LADs can be deducted from the contractor’s payments. Now it’s important to note that this amount is not a ‘penalty’; you can’t penalise the contractor for being late. However, genuine costs that you might incur such as additional rent if you’re in rented accommodation, or interest payments on financing, or storage costs for your belongings are genuine costs, and can be used to calculate the LADs figure.


So that concludes our three-part whistle-stop tour of the common pitfalls of self-build projects. I hope this is helpful, and please do get in touch if you have any questions.


 

View more blog posts.

Self-build Part 2: Regulatory and Statutory Issues

Self-build Part 2: Regulatory and Statutory Issues

Somewhat later than advertised, this is the second in our three-part series of blogs giving advice on how to avoid common pitfalls in self-build construction projects.

 

The first blog covered budgets and cost certainty, and this post will cover the second of the three main pitfalls to self-building: Regulatory and Statutory issues.

Read more

Close

Self-build Part 2: Regulatory and Statutory Issues

Somewhat later than advertised, this is the second in our three-part series of blogs giving advice on how to avoid common pitfalls in self-build construction projects.

 

The first blog covered budgets and cost certainty, and this post will cover the second of the three main pitfalls to self-building: Regulatory and Statutory issues. 

 

So what are the common issues?

  1. Starting on site with Key Detail and design decisions unresolved. Late decisions on finishes etc impacting on work already completed or resulting in project delays.
  2. Inexperienced self-builders not employing professionals to advise on regulatory compliance; lack of understanding leading to abortive work and additional cost
  3. Changes to design when already on site impacting on cost, time and regulatory compliance

 

The result?

Projects going over budget

 

The solution?

Ensure all key decisions and compliances are resolved before starting on site

 

The first of our common issues in this section really is fundamental. So many of those Grand Designs projects which go over budget within this section have done so because of a failure to prepare.

 

There are a number of issues which crop up time and again.

 

  1. Inadequate site or building investigation prior to tendering or cost planning. In the case of open sites this can mean levels surveys, soil investigations, arboricultural surveys. Where there are existing buildings it can also include detailed structural surveys, asbestos surveys, ecological surveys for bat roosting and many others. Your architect should advise you of what investigations and reports are necessary, but note that trying to save a few grand in fees by not having a full and comprehensive picture of your site or building will very often result in increased construction costs due to unforeseen issues.

 

  1. Unresolved construction details or material specifications. I’m sure I don’t need to elaborate too much on this…‘Winging it’ is never a cost saving option!

 

  1. Unresolved finishes and fit out details. No one expects you to have finalised every single decision in a construction project before the first spade hits the ground, but it is important to have an understanding of what decisions can be easily delayed, and when those decisions will become critical to the programme of the project. For instance, not choosing the exact toilet or sink is usually fine, but not finalising kitchen and bathroom layouts until late in the process can mean that services are not in the right location. A good contractor will have produced you a programme of work and will be able to give you dates by when outstanding decisions will need to be made in order to prevent delays to the contract. Despite this, you will need to bear in mind that even if you make a decision by the date the contractor asks, if you chose something that is on a long lead in, there will be a delay to the project.

 

 

So what do you need to know?

 

As you may be aware, the biggest technical hurdle for you and your design team to overcome prior to commencing on site is compliance with the Building Regulations. The Regulations are a set of 16 technical requirements that every building project must prove it can comply with to the satisfaction of the Local Authority.

 

So as a background, the actual requirement of each of the building regulations is in reality very small, usually no more than a paragraph outlining a particular fundamental objective for each document. However, each regulation is supported by what is known as an Approved Document, which set out the steps you need to take to prove you comply with the regulation.

 

It’s worth noting that the Approved Document sets out one method of compliance. This is often the easiest route but isn’t by any means the only route. If you are able to prove that you comply with the wording of the regulation by another means, and can agree that with the Building Inspector, you do not necessarily have to comply with the method set out in the Approved Document. This can be helpful if your building is particularly complex or innovative, and the Approved Document route to compliance may stifle the design.

 

Compliance with the regulations has two stages. The first is a submission of detailed drawings, specifications and calculations to Building Control, via what is known as a ‘full plans’ application, which must be made and approved before works can start on site. This submission can be phased but building control will require each element of the work to be signed off before it commences on site.

 

The second stage is Inspection. The Building Control officer will come out and inspect the works at key stages as the build proceeds to ensure that you are building in accordance with the details you submitted. Any changes along the way may result in Building Control requesting more or revised drawings or calculations.

 

Now, on some occasions, your contractor may suggest building something differently to what is on the approved drawings. There may be a cost saving involved, or it may just be that contractor’s preferred method. It’s vital to ensure that any change suggested is assessed for technical compliance by your design team and is signed off by building control. If there is no cost saving being offered by the contractor, bear in mind that you might incur additional design fees in having the change assessed by the architect or engineer, and so unless there are other contributing factors that make it worthwhile, it may not be in your best interest to agree to the change.

 

While there are certain changes that you would probably expect to be subject to the scrutiny of Building Control (such as structural or layout changes), there are a couple of others which are less obvious which I’d like to draw your attention to.

 

The first is compliance with Part L of the Building Regulations; Conservation of Fuel and Power. For new dwellings, you are required to produce what is known as a SAP calculation. This is a detailed set of calculations produced by a consultant which demonstrate the thermal and energy performance of the building. This calculation details every thermal and mechanical element of the building, from the orientation of the windows, to their thermal properties, to any natural shading available in the form of trees or other buildings, to the specification of the heating system.

 

You will be required to produce one ‘as designed’ calculation and one ‘as built’ calculation, so any changes you make to specification of thermal elements during construction will need to show compliance. So, for example, if you decided to change from a woodburning stove to an open fire, or change the insulation you use in the walls, I would advise checking with your consultant that any change will comply before undertaking the work. They can usually check this very quickly by simply changing a few entries in the software. This will prevent a nasty surprise later when the as-built calculation is produced, and the changes result in a fail.

 

The second, and the less well known, is the specification of your sanitaryware and taps. Under Part G (Sanitation, Hot Water Safety and Water Efficiency), you are required to provide a calculation to demonstrate that your home will use less than the Government set target of 125l water per person per day. In a nutshell you will be required to calculate the total water use of each of your WC’s and showers and taps, the total capacity of your baths. So where most people will think they can go out and buy whatever sanitaryware they like as long as it will fit the space, this is often not the case. If your Architect is involved in helping you choose the fittings, they will most likely undertake this calculation on your behalf and advise accordingly. If this is something you will be taking on yourself, a free calculator ‘tool’ can be found online, which requires you to input technical specifications from each item which you would be wise to do before paying for anything.

 

Finally in this section, it’s worth noting that Building Control services can be procured in two ways. Either directly with the Local Authority Building Control department, or increasingly via one of the many independent Approved Inspectors located around the country. There are pros and cons to each, and often you’ll find different local authorities provide better services than others.

 


So, a couple of other regulatory items to consider.

 

The revised Construction & Design Management Regulations came into effect in 2015, replacing an ineffectual previous version. One of the major changes between the previous version and this one is that significantly greater responsibility is placed on the clients of construction projects, whether domestic or commercial. If you’ve already appointed an architect for your project, they’ll have had to inform you of your duties under the CDM regulations, in particular advising on the appointment of a Principal Designer to manage the Health and Safety aspects of the design on your behalf.

 

This appointment needs to be made at the very early stages of the project and has to be someone actively involved in the design day to day. It therefore usually is a service offered by the Architect alongside their standard appointment.


The second item to be aware of here is the Party Wall Act 1996. This is in place to ensure that people undertaking adjacent to neighbouring properties cannot cause any damage to that property by the work they undertake. So works up to the boundary, or works whose footings may cross the boundary in certain prescribed ways must be agreed with the neighbouring property owner in the manner set out in the Act.

 

The Big One

 

Finally in this post we have one of the most common causes of delays and cost increases on site, which are changes to the design when the project is already underway. It is easy to understand, as sometimes it is difficult for particularly clients inexperienced in building and reading drawings to get a feel for a space before they are actually standing in it, and occasionally the reality is not quite what was expected, or an opportunity hasn’t quite been realised. Changes of course come in all shapes and sizes, from simply relocating an internal door at an early stage in the build, to the moving of a wall after it has been plastered and electrics fitted. Either way, there will be a cost and, usually, time implication.

 

So how can we avoid this? The onus falls jointly on the client and the architect and comes down to ensuring that you the client fully understands the plans and appreciates the implications of the design decisions being made during the design phase. The client needs to ensure that they speak up if there is anything they don’t understand or cannot fully visualise.

 

Alongside the more common Plan, Elevation and Section drawings, many Architects utilise sketches, physical models or three dimensional computer generated images to give clients an understanding of the spaces in their building. However, these are services which are not always included in an architect’s standard appointment, so if you think this is something you would require then speak to your architect when agreeing their appointment and ensure that it is included.

 

In the third and final blog post I will discuss the production of information for pricing by contractors, but it is worth noting here that if there are decisions which you feel you cannot make before work starts (such as finishes, kitchens, bathrooms etc), ensure that the contract allows Provisional lump sums to cover this work. If what you chose is cheaper, you will only pay the lower figure, but if it is higher you will be required to pay the extra. However, this ensures that there is at least an allowance within the contract sum for supplying and installing and ensures that it doesn’t get forgotten.

 

It is worth also noting that any changes which you wish to make which affect the external appearance of the house, such as moving or adding an opening, changes to external finishes or levels will usually require an amendment to your planning permission. This will require additional fees to be paid to your architect and the local authority and may cause a delay while the application progresses through the red tape.

 

Hopefully this post has given you some useful background to the regulatory and compliance issues facing you as a self-builder, please feel free to get in touch if you have any questions.


 

 

 

View more blog posts.

Most recent

Select month